Gym Expansion Project

We are nearing the final days in the first steps towards a working strength & conditioning room, upstairs spin studio and expanded main gym floor.  There will be some changes which are of note for users of the facility.  Should you have any questions please check out the attached FAQ or ask one of the friendly Leisureplex team.

Download Some of Our FAQ's

Key Project Dates & Access

The mini golf space has been redesigned over the past couple of months to accommodate a ground floor strength & conditioning room and upstairs spin studio.  While the strength & conditioning room is the last piece of the puzzle to fall into place for this project (proposed opening early April 2018), the spin studio will be up and running and remain in its new home for the near future.

Tuesday 30th January 2018

This is moving day.  From 9pm on Tuesday 30th of January the main gym floor and group fitness room will temporarily close.  This will allow us time to move all the equipment out of the current spin room, group fitness storage room and the main gym floor into temporary homes.  24-hour access to the gym will be unavailable until 9pm on Wednesday 31st January.

Wednesday 31st January 2018

Reopening day.  From 6am on Wednesday 31st January the temporary main gym floor will commence its short stay in the downstairs area of the redesigned mini golf space (future strength & conditioning room) with the new home of spin/sprint opening upstairs.  Access for the temporary gym and bike classes will be via membership band or barcode at the doors adjacent to reception/crèche, with all other group fitness classes being held on indoor courts and in function rooms for a short period from this date.  24-hour access to the temporary gym reopens on this day with entry into the building through the current 24-hour door, then follow the hallways to/from the mini golf space.



Friday 9th February 2018

Rehoming of Group Fitness classes.  Access to the group fitness room will resume on this date via a new entry point adjacent to the 24-hour door.  The new entry to the group fitness room will be locked outside of scheduled classes.



Early April 2018

Rehoming.  During the first weeks of April 2018 the expanded main gymnasium is due to be completed, allowing all the gym equipment to moved back onto the main gym floor.  This will also allow us to fit out the new strength & conditioning room, which will be open to Leisureplex full members, PT clients, Fitness Classes and casual entries.  More information on these aspects will be provided closer to the time.


Thank you for your patience while we work to bring
you an even better health and fitness experience.


If you have any questions, please let us know!